Old-style cross-ART dependency handling (deprecated)
This is deprecated. Please select a Solution-Train in the session-setup to create such a solution-level session. (>= onprem v2.10) and check the dependency handling here.
Make sure you've configured a Solution Level session.
- On the Team Board, Team A creates a Dependency, assigns the Dependency to the ART-team, links to the Feature and mirror the Dependency on the Program Board.
- Team A changes session and creates the same Dependency on the Solution Board in the swimlane of ART2
ART2 is now aware of that there is a Dependency to talk about with ART1 - Team B (ART2), the one which is in contact with Team A from ART1 to solve the dependency, creates A Dependency in its PI Planning session. Use the Team Board of ART1 to create the Dependency.
- Team B commits to a plan to solve the Dependency while continuously collaborating with Team A.
- Finally the Dependency is visualized as solved on the Solution Board